Dealer Log In
 
 
Forgot Password?
 
 
Project Southern Illinois University - Altgeld Hall - Earth Retention Carbondale, Illinois
Contractor FASTEEL Foundation Solutions, Inc., St. Louis, MO
Classification State University
Total Piers 41 Hollow Shaft Helical Piles and 26 Soil Nails
Completed December 2002 - 11 days to complete



Photo 1 - Initial Excavation
FASTEEL® Foundation Solutions, Inc. in St. Louis was asked to construct an earth retention system to provide lateral support of a vertical cut approximately 6-foot tall by 116 lineal feet wide while supporting the old foundation and three-story building. Other c o n t r a c to r s declined to bid o r attempt performing the work, stating it was outside their expertise.
The earth retention system was comprised of soil nailing helicals and helical piles, ULTrA brackets, steel wire fabric, reinforcement steel, bearing plates and a shot-crete facing of up to 18 inches. The first phase was to underpin the existing 106-year-old Altgeld Hall. This is a three-story, solid masonry construction, with a stepped footing of 3.5 feet thick at the base. Also adjacent to this vertical cut, FASTEEL® was to install new construction piers to support the proposed foundation wall of the addition.

Photo 2 - Preparing to underpin the stone foundation


Photo 3 - Installing the hollow shaft pier
Here was our challenge: To install helical piers to support the existing foundation wall. Because of the specifications of ¼” maximum deflection, it was important to underpin the existing foundation w a l l , thus taki ng surcharge loads off the soil and transferring the load through the pier shaft. Then to set pier ULTrA brackets to grade, in conjunction with steel cage, reinforcing steel and pour a grade beam at pier locations. (Grade beams were approximately 3'x3'x3')
The project’s general contractor would excavate approximately 58 lineal feet of wall to a 6-foot cut. below the existing foundation. FASTEEL® laid out and installed soil nailing helicals, using a mini-excavator. The installation process was field monitored throughout the installation. FASTEEL® furnished a pump, operator and two laborers to install the steel wire fabric and reinforcing steel, then set bearing plates and applied approximately 12-18" layer of shotcrete. Time required to complete the shot-crete wall was two days. Finally, we installed new construction piers to support the proposed foundation wall of the addition.

Photo 4 - Intermediate excavation


Photo 5 - Installing the soil nails
This phase of the construction was successfully completed ahead of our proposed schedule, which gave time for the general contractor to complete other areas of his project.


Photo 6 - Soil nailing and new construction piers in place


Photo 7 - Final Phase - applying shot-crete to walls

 

© 2007 Fasteel. All rights reserved
Site design by FCMIndustries,LLC.