Project Lawton Residence
Contractor Cut’N Break, Medford, Oregon
Engineer ADM Design Group
Classification Residential
Total Piers 35 Helical Anchors and 25 Titan HDP
Completed April 2001 - 1 week to complete



The pier is set and ready for the lift.
This residence had settled two and one-half inches. Interior and exterior piers were installed to an average depth of 24 feet. One corner lifted two inches and the rest of the residence was stabilized.


Installation


The lift is complete
The unique foundation of this home was nine feet deep in the front , tapering to a crawl space in the back.

 